Conduct surveys and apply for construction and environmental permits. Start of construction preparation from November 2021 to March 2022.
Start construction dock 1, 2 and 3 in March 2022 and completion in June 2023.
Last week a start was made with preparing the site of the Dutch Superyacht Tech Campus for construction. The water will be brought to the right depth and the land will be made ready for foundation work.
Omgevingsdienst Noordzeekanaalgebied, on behalf of the City of Amsterdam and Rijkswaterstaat, has approved the establishment and operation of Dutch Superyacht Tech Campus.